To follow production from another country, ask the factory for a short report every week in the same format: materials received, units finished, dated photos of your order and the estimated end date. If two reports in a row repeat the date without showing progress, it is time to send someone to the line.
Five or six weeks can pass between the deposit and the final inspection. If all you hear in that time is that everything is fine, you learn about the delay when there is no way left to recover it.
The fix is a report the factory can fill in within ten minutes and you can compare week against week.
The data in the weekly report
| Data | Why it matters |
|---|---|
| Critical materials received | Panels, compressors and boards often set the pace of the whole run |
| Units finished and packed | Shows whether progress is real |
| Photos of your order with your carton marks | Confirms the photos are of your lot |
| Changes or problems this week | A substituted component needs your approval |
| Estimated end date | If it moves, you want to know that same week |
A typical six-week calendar
| Week | What should happen | What to ask for |
|---|---|---|
| 1 | Materials purchasing | Bill of materials with arrival dates |
| 2 | Critical components arrive | Photos of the components in the store |
| 3 | First units off the line | Photos and video of a working unit |
| 4 | Production at normal pace | An inspection during production if the model is new |
| 5 | End of production and packing | Photos of the cartons with your marks |
| 6 | Final inspection | Inspection report before paying the balance |
Illustrative calendar for a catalog model with minor changes. Every factory and product has its own timing.
Signs that the order is slipping
- The end date repeats two weeks in a row with no progress in units.
- Photos always come from the same angle or never show your carton marks.
- The factory reports a missing component but gives no arrival date.
- The factory asks you to bring the balance forward to buy materials.
Any of these signs justifies a visit to the line. A visit in week three leaves room to fix things; by week six there is none.
Chinese holidays that move the calendar
National Day week, which starts on October 1, and Chinese New Year stop a large share of factories. If your production crosses either one, ask for the plant's closing and reopening dates and add them to the calendar from the start.
After Chinese New Year, many plants take a while to get back to pace because part of the workforce does not return. The first units after the restart deserve a closer look.
Frequently asked questions
How often should I ask for updates?
Once a week is enough for most orders. In the week production ends, daily contact may be worth it.
Who makes the visit to the line?
Your sourcing agent, a hired inspector or someone from your team if they travel. What matters is that they see the line with your order in production.